Our 2020 Projects

Jubail – Riyadh WTS Phase 3

Supply of: 16 PCS ROSSVALVE PRV 20” –DN 500 Class 150, Testing & Commissioning , Supply Spare Parts

Year: 2020

Location: Riyadh-Jubail

Client: SWCC

Saad Project

Supply and installation of Submersible pumping set together with related electric panels , transformers and generator, Supply and installation of DI Header piping with excavation and beck sling

Project Type: Well field

Year: 2020-2022

Location: Riyadh

Client: NWC

Implementation of raising the capacity of Al-Khumra plant 4 and Al-Khumra plant 3 in Jeddah

Supply , Installation 6 submersible pumps to pump the excess sludge include electrical panels, valves and connecting the pumps to the central SCADA system and all that is necessary 6 Decanter With all the necessary electrical panels and laying cables for washing pumps and polymer pumps. Construction of a metal hangar with an area of 36 m × 24 m × 7 m

Project Type: Water Treatment Applications

Year: 2020

Location: Jeddah

Capacity: 250,000 -300,000 M3/day (al Khomra Plant 4), 140,000 -190,000 M3/day (al Khomra Plant 3)

Client: NWC